A busy car dealership cannot simply put its entire parking area out of use for days at a time. In Dixon, Illinois, George Bros Paving LLC handled an asphalt maintenance project spanning more than 250,000 square feet while the dealership remained operational.

Our work included pavement cleaning, crack sealing, sealcoating, and parking lot striping. Hundreds of vehicles needed to be moved daily, which made access to the work areas a major part of this job.

Working Around Hundreds of Vehicles

With hundreds of vehicles needing to be moved each day, our commercial asphalt maintenance work had to account for a dealership that was still doing business, not an empty parking lot.

We worked in multiple phases, moving through the maintenance scope section by section. That let the job progress while the dealership continued operating.

The amount of pavement was one consideration; access to the areas being worked on was another. A completed section also needed to be ready when vehicles returned, so the work could not be planned around surface treatment alone.

Pavement Cleaning and Crack Sealing Across a Large Property

Pavement cleaning was one part of our scope. Before a surface treatment, cleaning matters because loose dirt and other material can interfere with its application. At this dealership, pavement preparation was part of a broader job that also included treating cracks and sealing asphalt surfaces.

We performed crack sealing to address openings in the pavement. The Federal Highway Administration explains that crack sealing is intended to limit water entering the layers below. That is different from applying a coating over a wider asphalt surface.

Sealcoating With Morning Traffic in Mind

The project also included commercial sealcoating. Our phased work included overnight periods and hours when the dealership was closed.

Every completed section needed to be fully dry and ready for traffic before the business opened the following morning. That next-day requirement mattered as much to the schedule as the work carried out during each shift.

Newly treated asphalt can look finished before it is ready for vehicles. Caltrans’ parking-area seal guidance describes keeping traffic off treated surfaces while the material cures. On a property with hundreds of vehicles to move, the difference between a coated area and a traffic-ready one matters.

Fresh Parking Lines and a Four-Day Finish

Our work also included parking lot striping. Yellow stall lines run across long rows against dark asphalt, marking out spaces on the dealership’s extensive paved areas. For a dealership moving vehicles daily, marked stalls are part of keeping the parking area organized.

The original schedule allowed five to six days. Our six-member crew completed the project in four, approximately one to two days ahead of plan.

We reached that finish while accommodating the dealership’s daily operations and the substantial vehicle movement required throughout the job.

Plan Commercial Asphalt Maintenance Around Your Property’s Needs

At a commercial property that stays in use, the work schedule matters alongside the pavement itself. Our Dixon project required multiple maintenance services and a phased approach at an operating dealership.

If your parking lot needs similar work, contact our team and request a commercial asphalt maintenance estimate.